FGT Critical Notice

Notice ID: 53381
Notice Type: Planned Service Outage
Critical: Y
Notice Status Description: Initiate
Reqrd Rsp Desc: No Response Required
Posting Date/Time: May 19 2025 7:35AM
Subject: May 2025 --- FGT WESTERN DIVISION AND MARKET AREA MAINTENANCE - Fifth Update
Notice Effective Date/Time: May 19 2025 7:35AM
Notice End Date/Time: Jun 1 2025 9:00AM
Notice Text:

FGT continues maintenance near FGT Compressor Station 4. This maintenance will probably continue through the end of May 2025. The first phase of this maintenance has been completed. During this next phase FGT will schedule up to 100,000 MMBtu/day from receipt points west of Station 4 to Wilson Coastal Bend (POI 100720). During normal operations FGT schedules up to 230,000 MMBtu/day through Station 4.

During this work zero volumes will be scheduled at the following point:

Pledger-Enterprise Receipt (POI 100022), Normal Capacity = 200,000 MMBtu/day

Major receipt and delivery points west of the maintenance area are Union Carbide-Seadrift Delivery (POI 16494), Tres Palacios Storage Receipt and Delivery (POI 78475 and 78476), Gulf Shore Markham Receipt (POI 78427), and Wilson-Coastal Bend Delivery (POI 100720). During this maintenance volumes for receipt/delivery points west of the maintenance area must be scheduled from delivery/receipt points west of the maintenance area.

The first major delivery point east of the maintenance area is Rosharon-Brotman (POI 100775). The first major receipt point east of the maintenance area is NGPL Jefferson (POI 10240).

FGT continues maintenance at FGT Compressor Station 7. This maintenance will continue through the end of May 2025. During this maintenance FGT may schedule up to 375,000 MMBtu/day through Station 7, During normal operations, FGT schedules up to 465,000 MMBtu/day through Station 7.

FGT will be performing maintenance on its FGT Compressor Station 8. This maintenance is scheduled to begin on May 28, 2025 and is to be completed by end of gas day May 30, 2025. During this maintenance FGT will schedule up to 900,000 MMBtu/day through Station 8. During normal operations FGT schedules up to 1,075,000 MMBtu/day through Station 8.